Concessions

Details of works planned for the Kirkcaldy area in 2024/25 are included below.

Key to progress indicators:

Works still to commence onsite Planned
Works in progress Started
Construction works complete Complete
Construction works postponed Postponed

Road improvements planned for 2024/25

WardTown Location (Click for map)BudgetProgress
12 Kirkcaldy A910 - Nicol Street - Esplanade to Veterinary Surgery £190,500 Complete
12 Kirkcaldy A921 - The Path / Nether Street - High Street to Ravenscraig Roundabout £342,500 Complete
12 Kirkcaldy A921 - Rosslyn Street £391,000 Complete
12 Kirkcaldy A915 - Randolph Road £375,500 Complete
12 Kirkcaldy C96 - Hayfield Road £115,000 Complete
10KirkcaldyChapel Level Phase 2 - Junction at Fair Isle Road / Robert Adam Drive and W/B to Broom Road R/A ( W/B only )£400,000Complete
12KirkcaldyTweed Street Complete

Footway improvements planned for 2024/25

WardTown Location (Click for map)BudgetProgress
10 Kirkcaldy Greenloanings - Phase 2 £44,000 Complete
12 Kirkcaldy Tweed Avenue £37,500 Complete
11 Kirkcaldy Bennochy Road - Phase 2 £87,000 Started
10 Kirkcaldy Dunearn Drive - Community Centre to Templehall Café (both sides) £123,500 Complete
10 Kirkcaldy Barry Road - In front of primary school £41,000 Complete
12 Kirkcaldy Beatty Crescent - Macindoe Crescent to Overton Road £91,000 Complete

Lighting improvements planned for 2024/25

WardTown Location (Click for map)BudgetProgress
12 Kirkcaldy Tweed Avenue £24,000 Complete
11 Kirkcaldy Bennochy Road Ph 2 £54,000 Complete
12 Kirkcaldy Millie Street / Junction Road £29,500 Planned
12 Kirkcaldy Transportation Car Parks - St Clair Street / Junction Road £32,500 Planned
9 Kinghorn Long Craigs Terrace £42,000 Complete
10 Kirkcaldy Dunnikier Estate  - Braehead Road £21,000 Complete
11 Kirkcaldy William Street, Methven Road, James Grove £87,000 Planned
12 Kirkcaldy Smeaton Area - Hayfield Rd, Holly Pl, Veronica Cres, Sycamore Ave, Oaktree Sq & Oaktree Court £123,000 Complete

Traffic Management improvements planned for 2024/25

WardTown Location (Click for map)BudgetProgress
  Kirkcaldy Road Crash Improvements - Bankhead of Piteadie £3,500 Complete
9 Burntisland A921 Aberdour Road (buildout) £20,000 Complete
10KirkcaldyBlairmore Road - Traffic Calming£20,000Complete
10KirkcaldyBroom Gardens near junction with Broom Road£10,000Complete
9KirkcaldyBalewarie Road west end£20,000Complete
9KinghornA921 Kirkcaldy Road near Croft an Righ£30,000Complete
12KirkcaldyBoreland Road£30,000Complete
11KirkcaldyDunearn Drive (review Traffic Calming)£35,000Complete

Structural Services planned for 2024/25

WardTown Location (Click for map)Budget Progress
    

Planned patching programme for 2024/25

WardTown Location (Click for map)Budget Progress
    

Cycleways programme for 2024/25

WardTown Location (Click for map)Budget Progress
9BurntislandLinks to Burntisland Rail Station from NCR76 Link East Ph2 & Ph3£50,000Complete