Road improvements planned for 2024/25

WardTown Location (Click for map)BudgetProgress
8 Rural Road B922 - Cluny Roundabout to Railway Bridge £164,500 Planned
8 Rural Road B981 - Liza Brae to Jamphlars Road £524,000 Complete
7 Cowdenbeath Leuchatsbeath Drive - A909 to Johnston Park £361,000 Planned

Footway improvements planned for 2024/25

WardTown Location (Click for map)BudgetProgress
8 Crosshill B920 Main Street £37,000 Started
7 Kelty Main Street - Seafar Drive to White Gates Terrace £43,000 Complete
7 Cowdenbeath Broad Street - Joe's Food Bar to Fountain Roundabout £62,000 Complete
7 Cowdenbeath Raith Avenue - Broad Street to Park Street £5,500 Planned
7 Crossgates Droverhall Avenue Ph1 - B925 Mossgreen to Property No 42 both sides £104,000 Started

Lighting improvements planned for 2024/25

WardTown Location (Click for map)BudgetProgress
8 Ballingry Flockhouse Avenue & Path 178/972 - Columns 1 to 5 £27,000 Planned
8 Ballingry Navitie Park - Columns 17 to 23 £24,000 Planned
7 Hill of Beath Torbeith Gardens £30,000 Planned
8 Ballingry Malcolm Street £39,000 Planned
8 Lochgelly Zetland Place, Buller Street & Dundas Street £30,000 Complete
8 Cardenden Carden Castle Park £78,000 Started

Traffic Management improvements planned for 2024/25

WardTown Location (Click for map)BudgetProgress
6, 7 & 9 Rural Cowdenbeath to Burntisland A909 (RARP) £40,000 Complete
6 & 7 Rural B981 Inverkeithing to Crossgates £25,000 Planned
7 Crossgates Kirkcaldy Road (Puffin crossing & Footway widening) £50,000 Complete
8 Ballingry B920 Lochleven Road Near Ballingry Crescent £30,000 Planned
7 Cowdenbeath Woodend Place Allan Park to Gardiner Place £10,000 Planned

Thin Carriageway Surfacing Programme for 2024/25

WardTown Location (Click for map)Budget Progress
7KeltyBeechbank Crescent Complete
7KeltyElmwood Terrace, Laurel Avenue, Maple Terrace, Dullomuir Drive Complete
7CowdenbeathGreenbank Drive Complete
7CowdenbeathWoodbank Complete
7CowdenbeathWest Lane Complete
7CowdenbeathDalbeath Crescent Complete
8LochgellyMelgund Place Started
8LochgellyMcGregor Avenue & Adam Place Started
8LochgellyGordon Street & Adamson Road Started
8LochgellyGarry Street Started
8LochgellyDewar Street & Timmons Park Started

Planned patching programme for 2024/25

WardTown Location (Click for map)Budget Progress
    

Cycleways programme for 2024/25

WardTown Location (Click for map)BudgetProgress
  Cowdenbeath A909 Kelty to Cowdenbeath Phase 3 £320,000 Complete
  Lochgelly Fife Cycle Park to Lochore Meadows £180,000 Started
  Cowdenbeath A909 Kelty to Cowdenbeath Phase 2 £180,000 Started
  Crossgates Fordell Firs (2022 Crossgates to Fordell Firs new path) £30,000 Planned